CRANE CREEK RESTORATION PROJECT

823 Brothers Ave, Melbourne, FL 32905​

FOOD FOREST

COMMUNITY SPACE

RESTORATION SITE

​

2_edited.png
3_edited.png
4_edited.png

Overview:

The Crane Creek Restoration Project is a project located on 0.49 acres at 823 Brothers Ave in Melbourne, FL. The site is currently a vacant site, with a vision of turning into a community food forest and restoration site. The site will include fruit trees, native and edible plants, raised garden beds, and stormwater retention features. The project will not only help increase access to freshly grown produce for families living in a food insecure area, but will support storm water mitigation and promote sustainable, healthy living. It will also teach the principles of environmental justice to the community who will learn about stormwater mitigation,  permaculture principals, soil testing, and more. 

​

Project Goals:

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​​Draft Design Options:

​

​

​

​

​

​

​

​

​

​

​​

​

​

​

​

​

​

​

​

​

​

​

​

 

 

 

 

 

 

 

Photos of Initial Schematic Design:​

Fresh Oranges Display

01

Improved access to fresh, healthy food through the installation of a food forest designed for long-term, perennial harvests.

Child Observing Nature

02

Restored ecological function on a previously degraded, flood-prone site through nature-based solutions like native plantings and rainwater harvesting. 

03

Reduced urban heat island effect by planting trees and vegetation to cool the landscape, provide shade, and create a more comfortable and livable microclimate on site.

IMG_4341.JPG

04

Implementing a design that is community-led

481228255_1042232734616361_4179756938799948676_n.jpg

05

Intergenerational education and empowerment

Community Food Pantry

06

Stronger community resilience

Timeline and Status:

  • Preconstruction: Design and Permitting​​

    • Start Date: 2023​

    • Estimated Completion: 2027

  • Implementation, Phase 1A: Features of work will include perimeter fence, well and well pump, fruit trees, native and edible plants, and raised garden beds.

    • Start Date: 2026, Q3

    • Estimated Completion: 2026, Q4

  • Implementation, Phase 1B: Features of work will include a ~600 sq ft covered pavillion, signage, and minor stormwater retetion features

    • Start Date: 2026, Q3

    • Estimated Completion: 2027, Q3

  • Implementation, Phase 2: Features of work will include a parking lot, 100 sq ft air conditioned office and meeting space, ADA accessible walking path​

    • Start Date: 2027, Q1​

    • Estimated Completion: 2028, Q4

Funding

THANK YOU to the following donors, sponsors and grant agencies for helping push this project forward:

​

​

​

​​

​

​

​

​

​

​

​

​​

​​​​

​

​​​​​​

​

​

​

One Lagoon.PNG
NFWF.PNG
Community Foundation For Brevard Logo.png

Partners

THANK YOU to the following partners for helping push this project forward:

​

​​​​​​

​

​

​

  • Facebook
  • LinkedIn
  • Instagram

© 2017 by Little Growers Inc. Proudly created with Wix.com

Call us:

(321) 330-7916

​

​

​

Find us: 

FIND US AT:

​

MELBOURNE SITE: 823 Brothers Ave. Melbourne, FL 32901

​

Aquaponics Farm Space: Coming Soon

bottom of page